View online |
![]() |
![]() |
SH3 New Plymouth to HāweraProject update |
![]() |
![]() |
28 March 2025 |
![]() |
![]() |
||
![]() |
Now and Then: how the Mangorei Road intersection looks today and an indicative artist's impression of how it will appear once completed in the first half of 2026. Roundabout takes shape at Mangorei intersectionUsers of SH3 south of New Plymouth will have seen the great progress made since work started on the construction of a roundabout and associated improvements at the Mangorei Road intersection last November. Since then contractors have carried out a wide variety of works, while working hard to minimise disruption for local residents and those travelling through the intersection.
To date the works have included:
Elsewhere on the project, vegetation clearance has been completed on SH3 between Junction St and Burgess Hill, following lizard salvage and relocation. Over the coming months at the Junction St intersection, crews will widen the highway to allow for the marking of widened centreline, maintain driveway entrances of residents impacted by the widening, install new stormwater lines, as well as upgrading existing and installing new lighting. Along the corridor contractors are busy applying second coat seals at various locations where safety improvements have been completed over the last 18 months. When we rebuild or make changes to the road surface, we apply a chipseal finish and need to come back later to carry out a second coat seal. This locks in the seal to make it waterproof and keep it stronger and safer for longer. To prevent large traffic queues and travel delays on these busy sections of road, the work will be completed at night, when traffic volumes are lowest. Design work for further possible safety improvements at sites over approximately 25km between Egmont Village and Eltham is almost complete. These designs will be retained for future use when construction funding becomes available. |
![]() |
![]() |
Stop/Go traffic management from 30 MarchAs outlined above, crews will soon commence the reconstruction of the road surface and underlying road structure at the Mangorei Road intersection. The work involves removing existing road material and replacing it with aggregate and asphalt, to improve the safety and resilience of this busy location. To complete this as safely and efficiently as possible, this work will be completed at night (6pm-6am, excluding Friday and Saturday nights) under stop/go traffic controls, with access to/from Mangorei Road at SH3 closed during works. This work cannot be done under contraflow (two-way) traffic controls, so it will be completed at night when traffic volumes are lowest, to prevent large traffic queues and travel delays on this busy section of road.
• This work is scheduled to begin on Sunday 30 March and is expected to take approximately 3 weeks to complete, weather permitting. |
![]() |
![]() |
More information |
![]() |
![]() |
For more information on the SH3 New Plymouth to Hāwera project, contact us at taranakiprojects@nzta.govt.nz Visit our website www.nzta.govt.nz/projects/sh3-new-plymouth-to-hawera |
![]() |
|
|