Skippers Lane
Works on the eastern side
Stormwater installation on the eastern/state highway side of Skippers Lane is almost complete. Road pavement work will likely be finished by the end of next week, with kerbing preparation following immediately behind.
Kerb and footpath work
Kerb preparation and pouring will get underway from next week, moving from the eastern to the western side of Skippers Lane.
The concrete pour for kerbing on the western/shopfront side is booked for the last Saturday in September (weather permitting) and steel plates will be used to ensure access to any businesses that are open. The pour will be done from north to south.
The footpath will be laid in sections beginning late September or early October.
Parking availability
A reminder that public parking is available during the daytime from 8am-4pm behind the Pioneer Restaurant and Bar.
This parking is accessible from the service lane that runs between Skippers Lane and Maritime Lane. From 4pm parking is for Pioneer customers only.
|