Fulton Hogan update
Petone Park & Ride
Works are now complete in the Petone Park & Ride car park. A new one way system has been incorporated into the design, which allows for the new shared path beside the station platform.
A bike shelter for train commuters who travel by bike is also planned to be installed at the station later this year.
Hutt Road and Parliament Street
Construction of the pump stations on Hutt Road is ongoing. These facilities will help discharge rain water from the underpasses into the storm water network.
Work has been extended, please follow the temporary traffic management which is in place on the Hutt Road, near to where the underpasses are. This is to ensure the safety of our crews and other road users.
The anti-graffiti paint application has been weather dependent and is ongoing at Petone and Normandale underpasses and along the retaining walls.
Next to SH2
Surfacing works continue throughout May along the cycleway (the main part of Pito-One to Melling).
Right now, we're up to surfacing the main cycleway next to the Dowse Interchange. Once this is complete, we'll be turning our attention to the installation of CCTV, lighting, signage, and line marking.
We're also working to tie the shared pathway sections in around the Hutt Rd/McKenzie Ave and Parliament Street/Normandale Road bridge areas.
|