View online |
SH2 Wairarapa highway improvements |
26 July 2023 |
July 2023 updateWelcome to our July update on the SH2 Masterton to Carterton safety improvements project. As we approach the later stages, we thought it would be good to highlight the milestones achieved over the past few weeks and provide a glimpse of what's coming up. Here's a summary of our recent activities and upcoming tasks: |
||
Above: the finer points of making a traffic island. Ngaumutawa roundaboutAt the Ngaumutawa Road roundabout, the asphalt is nearly done except for the final seal layers. The final sealing layers will be completed later this year, when weather conditions are warmer and drier, and the road surface has had a chance to settle and bed in. The traffic island kerbs are complete. The concrete infills for the islands are to follow in the coming weeks. Work on the roundabout’s footpaths and driveways heading south are progressing well, and construction of the retaining wall on Norwood corner is underway. |
||
Norfolk Road roundabout
We’ll soon place the final concrete sections to form the complete circle of the structure. The roundabout is an innovative design made from 47 specially moulded concrete blocks each weighing 3.5 tonnes. |
||
Wiltons Road roundaboutWe’re working on finishing the traffic islands, and have started some landscaping. If you’ve driven through this area recently, you’ll notice some of the new planting has taken place. As with the other roundabouts, the final seal layers will be completed when the weather is warmer and drier. |
||
Above: the new turnaround bay at Clareville, looking southward to Carterton. Clareville turnaround bayThe turnaround bay at Clareville is expected to open soon. It provides southbound drivers a safe area to cross the highway, pull into, and wait for a safe break in traffic before heading north. It’s been designed to accommodate large vehicles, including semi-trailer trucks. |
||
|
Other project highlights
There’s been a lot of road widening and swale drain work between Wiltons roundabout and the turnaround bay. Some driveway work continues in the newly widened areas. Installation of guardrails at Parkway Creek is underway. |
||
Road closures and stop/go traffic managementAreas of work which are disruptive to traffic, and requires stop/go traffic management, is performed during nightshifts where possible, to minimise disruption. |
||
More information |
||
Thank you to everyone using SH2 for your patience, care and understanding while driving past our work sites.
If you know anyone who might be interested in these updates, they can sign up on this webpage here. |
||
|
|