North of Katikati
Trig Road to Athenree Gorge (Sections 2 and 3)
The two sections, Trig Road to Mathers Road and Mathers Road to Athenree Gorge have been combined. Since our last update the weather has been kind and our contractor HEB Construction has made good progress on the following activities:
-
Installing environmental controls to protect waterways.
-
Removing trees.
-
Relocating services such as fibre.
-
Extending drainage channels where the road has been widened.
-
Earthworks and road widening from Trig Road to the start of the Athenree Gorge south bound lane.
-
Earthworks and road widening from Trig Road to south of Woodlands Road northbound lane.
These activities will continue under Level 3 and will head south to the Athenree Gorge. Followed by final touches such as laying line marking and installing barriers in some sections.
We are still on target for completing these sections by mid-2021.
Athenree Road to Tanners Point Road (Section 4)
Underground services have been located, such as water, electricity and fibre. The team used a radar to pinpoint where they were and then uncovered them by hydrovac, which, as the name suggests, involves high pressure water and suction. This non-digging method reduces the risk of accidentally cutting into a service line during earthworks. Information collected from this work is being used by the design team as they finalise the detailed design for construction.
Trees identified as either in the path of road widening or otherwise potentially hazardous to road users have been removed.
Tanners Point Road to Kauri Point Road (Section 5)
Preliminary work has started, such as identifying where underground services are, using the same process outlined above. Information collected from this work is being used by the design team as they finalise the detailed design for construction.
Kauri Point Road to Lindemann Road (Section 6)
Preliminary investigation work has been completed and designs are being finalised in this section so the main work can start later this year.
|