Project progress
Activities next week (22 - 29 November)
Please note that these works are weather dependent and may be delayed.
During the day (from 7am to 6pm)
Zone 1 (from Pukaki Creek Bridge to East of Campana Road)
-
T-intersection to be completed at Campana Road
-
Kerb and channel work at Pukaki Creek Bridge
-
Earthworks continue on the north side of Pukaki Creek Bridge
-
Drainage line installation continues from Orrs Road to Pukaki Creek Bridge
-
Concrete barriers installed at the southeast corner of the Campana intersection.
Waokauri Creek Bridge
-
Transition barrier works
-
Installation of duct brackets
Zone 2 (from East of Campana Road to the SH20 interchange)
-
Kerb and channel to be poured on the north side of the widening section close to SH20 interchange
-
Streetlights to be installed between Prices Road and Black Bridge Nurseries
-
Temporary barriers to be removed between Waokauri Creek Bridge and Manukau Memorial Gardens
-
Excavating swales at 457 Puhinui Road and box cuts completed just past Prices Road on the north side of the carriageway.
Utilities (throughout the site)
-
Protection work will be carried out for the fuel lines across SH20B at the Campana Road intersection. These works are programmed to continue for two weeks.
-
Preparation for a localised power shutdown planned for mid-December.
At night (all zones from 9pm to 5am, Sunday to Thursday)
-
Ongoing drainage works to verges and road crossings
-
Continuing asphalt pavement replacement along the existing carriageway.
There will be no through traffic from SH20 interchange to the Tom Pearce Drive roundabout. Please follow the posted detour signs on SH20B.
Safety
SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:
-
All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
-
Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
-
Night time detours will likely be in place from Sunday to Thursday between 9pm and 5am. Please follow the posted detour routes
-
The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph. Please drive safely and allow extra time for your journey.
Looking Ahead
An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.
Please drive safely and allow extra time for your journey.
|