QEII Drive piling and wall reconstruction update
The deconstruction of the wall panels and abutments is going well and is ahead of schedule - the night work for this is finished and the piling is being set up.
All going well, the piling will take six to eight weeks. This work will be noisy, so thank you for your ongoing patience and understanding, we really do appreciate it.
Following the piling, we will reconstruct the ramps and walls and then place the bridge beams early next year.