Project update

21 October 2020

Story
 
 

 
Story

Chaneys On-ramp closed permanently

To connect the new CNC motorway to SH1 some changes are needed. As planned, the existing Chaneys on-ramp is being removed to make way for the CNC northbound lanes.

We have left the Chaneys On-ramp open for as long as we can, but we now need to close it for good from Tuesday 27 October to complete work in this area. 

Closing the Chaneys On-ramp means there is no access to SH1 at this point. If you want to use SH1 from Marshland Road you can access it by either using QEII Drive, Prestons Road, Radcliffe Road or Belfast Road to access Main North Road and then SH1. These roads all have traffic signals, making a right turn onto Main North Road easier. (The Belfast Road signals will be activated in the next few weeks.) You could also continue on Marshland Road and Main North Road to enter SH1 from Ohoka Road. 

Read more

Story
 
Image

 
Story

Cranford Street night work

Work continues between PlaceMakers and the new Cranford Street Roundabout.

To minimise traffic impact, we will do this work at night. This work started on Sunday evening 18 October and will continue each night until Thursday 22 October, work will start around 7pm each night.

During this night work traffic will be managed with lane shifts. The work will involve digging, milling, truck movements and compacting the ground before asphalting, so nearby residents will hear the noise from the machines and the crew working at night.

Story
 
Image

 
Story

What do you think is important for Greater Christchurch in 2050?

While the year 2050 might seem a long time away, to meet the future needs of our communities, we need to start planning now. 

That’s why the Greater Christchurch Partnership is creating a new plan for our sub-region with everyone that has an interest in the area. The partnership consists of councils, the district health board, Ngāi Tahu and government agencies such as Waka Kotahi.

Greater Christchurch 2050 will describe the kind of place we want for our future generations, and the actions we need to take over the next 30 years to make it happen.

What you do think Greater Christchurch should look like in 30 years.

Do the short survey 

It should take around 5 minutes to give us your feedback. You will be able to give feedback until the 8th of November 2020.

For more information and to do the survey: greaterchristchurch.org.nz

Story
 
Image

 
Story

Drone flyover of the project

Check out our latest drone footage here

Story
 
Image

 
Story

Most popular question - When will you be finished?

The new CNC motorway is on track to be completed in mid-December this year.

And the cycle path will open at the same time.

Story
 

 
Story

Questions and Feedback

Hello everyone

We all really enjoy the feedback, comments and questions we get about the CNC project. If you wish to get in touch you can email me at melanie.williams@cncalliance.co.nz or info@cncalliance.co.nz

You could also take a look at our Frequently Asked Questions webpage. Or your question could be answered in one of our Videos.

Story
 

 
Story

Tell a friend

Please feel free to forward this email to others who may be interested or affected. 

Story
 

 
Story

Kind regards

Melanie

Story
 
Image

 
spacer

More information

spacer
 
 
Story

For more information on the Christchurch Northern Corridor project, visit our website www.nzta.govt.nz/CNC