Project update across all five sites
The project team are progressing with works across all five sites, helped by the recent good weather.
In particular, Sites 7 and 9 are coming along really well, with retaining walls at and near full height.
On the other hand, Sites 11 and 13 continue to provide us with big challenges that we didn't anticipate at the beginning of the project. Leaching water and poor ground conditions make it harder to reach a solid foundation to build up the retaining walls in the narrow and steep gullies.
So while progress is steadily being made, unfortunately it is not as fast as we would like.
Be assured, we are working as quickly as we can, where we can, and are aiming to have two lanes open later this year.
Below is an update on each of the five sites:
Site 6: Nearing excavation depth, can then begin construction of the pre-cast foundation pad and placement of rip-rap (large boulders which manage the water runoff).
Site 7: Retaining wall now at full height, and works have started to enable the new culvert to be extended across the rest of the road.
Site 9: Construction of the retaining wall is a third of the way completed, with good progress being made due to the recent dryspell of good weather.
Site 11: About to start construction of the retaining wall, but leaching water from the excavated bank is causing severe issues; currently working on a solution.
Site 13: Excavations have reached the final design level, but poor ground conditions (decomposed rock and weak soil) continue to provide challenges. However, the crew are making headway and construction of the foundation pad is expected to be cast in place next week.
See the latest site images here.
|