| View online |
![]() |
TREC Tairāwhiti recovery updateIssue 43 |
|
10 April 2026 |
Tēnā koeIn this issue we share a video showing recent work at the Hakanui Straight flood resilience project on State Highway 2 (SH2). We also share updates from our State Highway 35 (SH35) projects at Mangahauini Gorge, Hikuwai Bridge, Rotokautuku (Waiapu) Bridge, and Maraehara. Thanks for your ongoing patience and support as we continue our Cyclone Gabrielle recovery mahi. With a weather warning in place for this weekend, please stay safe. Keep an eye on the NZTA Journey Planner for up-to-date travel information and follow their Facebook page. |
||
SH35 Mangahauini Gorge – upcoming traffic changesWork is progressing at Mangahauini Gorge as crews continue strengthening the river control structures that protect SH35 during periods of high river flow. With structural reinforcement now in place, the next phase involves:
To safely carry out this work, upcoming changes to traffic management will begin from mid‑April. From next week through to August, the road will be single‑lane with 24/7 temporary traffic lights with up to 5 minutes delay. As works progress, traffic will switch between the northbound and southbound lanes, but will stay single‑lane until the work is complete. When traffic shifts to the northbound lane road users will be on the new road alignment, which is a big milestone for this project. These traffic shifts allow crews to safely access different parts of the embankment and river structures while keeping SH35 open for the community. Mangahauini culvert work Around 500 metres south of the main Mangahauini site, culvert (large pipes) and drainage work will also begin next week. A new culvert will be installed under the full width of the road which requires excavation, so traffic will need to share a single lane while construction is underway. The road will be reduced to one lane under stop/go traffic management Monday-Friday between 7am and 6pm. The works are expected to take 9 weeks to complete, although this may change depending on weather and ground conditions. A 30km/h speed restriction will be in place, and delays of up to 5 minutes are likely. Thanks for driving safely so our hard working crew can get home to whānau after each shift. The new alignment of the road being built is on the right-hand side. |
||
SH35 Hikuwai Bridge progress and kura connectionWith the new Hikuwai Bridge piling now complete, crews are focused on pile caps, abutments (structures at the ends of the bridge) and building a Mechanically Stabilised Earth (MSE) wall. The wall will be built between the bridge abutments and the existing ground, holding the road above in place. We also had a special visit from Te Kura o Mata, located inland from Tokomaru Bay. Tamariki were treated to an up-close view of the works by Senior Project Manager Fred Witton. You can also take a closer look at the intricacies of bridge piling on page 6 of our Hikuwai photo spread in our recent TREC Pānui. Left to Right: The northern abutment is making good progress; Te Kura o Mata on-site with Fred Witton on right. |
||
![]() |
||
Foundations locked in at Rotokautuku (Waiapu) BridgeCyclone Gabrielle caused serious flooding and erosion beneath the Rotokautuku (Waiapu) Bridge on SH35 near Ruatoria. It damaged the riverbank and parts of the bridge structure. We’re working on rebuilding and strengthening the riverbank and adding long-term protection to guard it from future flood events. Beneath the surface, crews have been busy locking the riverbank protection structure into place, burying hanbars (large concrete blocks) deep within the riverbed to form a solid anchor. With the first row of the foundation secured using the hanbars, an initial row of dolosse (a different type of large concrete block) has been placed, as shown in the photo below. Rock armour (large boulders) will be installed on the riverside to protect against scouring. Following completion of the foundation works, rock bags will be installed with additional dolosse placed above. This will form a layered protection system to provide long‑term stability and erosion resistance for the riverbank. This layering will continue for a number of weeks, with the project expected to be completed mid-2026. First line of dolosse (large concrete blocks) installation has now been completed. |
||
![]() |
||
Steady progress at MaraeharaCrews are busy at Maraehara on SH35 repairing a section of road that failed after Cyclone Gabrielle. A 38 metre long counterfort drain has now been installed to improve drainage and reduce movement in the area. These drains are full of perforated holes to capture water from inside the ground and keep it moving away. A shear key is also being constructed as part of the repairs. This is an engineering technique used to act as a barrier to the hillside moving and underground drainage to improve the ground stability.
|
||
State highway snapshotBelow is a snapshot of construction works either underway or coming soon. You can also view completed, current and future work sites on our interactive map. SH2 underway
SH2 coming soon
SH35 underway
|
||
![]() |
Whakapā mai – Get in touchIf you spot an issue at a work site after hours, call 0800 4 HIGHWAYS (0800 444449). Sign-up to receive these regular newsletters:
Local road network Gisborne District Council is responsible for local roading recovery projects. More information. |
||
|
||||||||||||||||||||||
|