Progress update
Over the past three months there's been noticeable changes on the Loop Road project. The bridge construction is progressing well, with all eight large bridge piles built on schedule. We’re also pressing on with other work around the site including the edge barriers, safety barriers, and handrails that are being made, ready to be installed.
Support frames are in place on the northern side of the site, and work on the foundation is progressing well. On the southern side of Otaika Bridge, the foundation and support structures have been set up and poured, ready for the beams.
On this project we are using Super-Tee beams, these will create the span between the bridge and the abutments or piers. The ‘super’ part of their name comes from their strength, as these beams are loaded with pre-stressed steel cables. Along with reinforcement, this allows them to span further than normal beams.
The 60-metre retaining wall and capping beam along Otaika Creek is also finished. In addtion, ground anchors have been installed and tested. Also known as tiebacks, these are rods or bars that are installed into the ground to provide extra stability.
Other work that has been completed includes installing streetlights, stormwater lines, and other utilities. One of the layers in the road under the asphalt (called the pavement subbase) has been brought in and installed on the northern approach.
Concrete kerbing and work on the shared path has started on the northern side, along with installation of barrier posts. Approximately half of the native landscaping is complete, with mulch, coconut matting, and native plants installed on topsoiled areas, creating a cost effective and environmentally friendly finish.
|