Onsite update
Construction of the Old Māngere Bridge Replacement is well underway. With the first bridge span completed, the team have moved onto the second span and so far we have placed two of the seven concrete beams.
We are now removing the temporary works around our largest pier (pier two) which includes the scaffolding, formworks and the sheet piles which created the cofferdam. Due to the size and scale of this pier, this work will be completed around the end of June.
Another team is working on the second large pier (pier 3), which supports the other side of the central steel deck and arch. The pile cap and plinth (base) have already been completed and the team is now forming the four 14m tall ‘v’ shaped columns which the bridge deck will sit on.
We also have two more small piers (pier four and seven) located on the southern side underway.
|