View online |
SH2 Wairarapa highway improvements |
3 November 2023 |
Welcome to our November update
We’re pleased to inform you that the final road surfacing works for the Masterton to Carterton Safety Improvements Project started this week and will continue through to mid-December. We’re hoping for a good run of warm, dry weather to ensure that we can complete what is the final phase of the project. Work will mostly be done at night. Drivers travelling south from Masterton must be prepared to detour between Cornwall Rd and Hughes Line from 8 pm and 6 am, as required. Driving between Masterton and Carterton may mean having to a detour at night when crews are on the ground.
Please factor in potential delays to travel plans. Our contractors are making every effort to get this specialised work done in the shortest time possible without compromising on the care needed to build this critical piece of highway. |
||
A view of the highway before the median barriers were installed. |
||
Mid-December target
Jetesh Bhula, Waka Kotahi Regional Manager Infrastructure Delivery, says the work will take around six weeks to complete but it must be done now so that the highway is ready for the summer holiday season. |
||
Bruce Pauling takes time to share his thoughts, pictured here at the Clareville rest stop. Some thoughts from Bruce Pauling about the project
“The Masterton to Carterton SH 2 safety improvements are nearing completion, and ‘fingers crossed’, the weather will ‘play ball’. Following the technical planning and mandatory requirements for consultations, once the initial works began, contractors worked around the clock for many months to arrive at this near completion point. Commuters were of course impacted, however doing all the ‘mahi’ over this period meant the project is to be completed in a much shorter time frame, rather than dragging on for a couple of years. I think Waka Kotahi and contractors should be congratulated on this huge safety project. We have already seen three ‘hits’ to the centre ‘wire rope’ barrier, which potentially prevented head-on collisions which often result in deaths and serious injuries. The barriers will prevent future collisions of this nature, protecting people travelling along this corridor. The Wairarapa Road Safety Council applaud any safety improvements that reduce the incidences of crashes, particularly in these high-speed environments.”
Bruce Pauling |
||
Building New Zealand roads – a quick overviewCheck out this short video showing Rob Campbell, Waka Kotahi Regional Manger Waikato/BOP, talking about why we build our roads the way we do |
||
Thank you again!We’d like to take this opportunity to pass on our sincere thanks for your patience during the last 16 months of the project’s investigation, design, consenting, and this year, construction. Combining what would usually be two years of roadbuilding work into a shorter time frame was always going to be a big ask. Residents and business owners along the works corridor have been impacted more than most. We value the patience, tolerance and understanding from local residents and communities. The entire project team is grateful for the accommodations people have made while we’ve been working in your community. |
||
More information |
||
If you know anyone who might be interested in these updates, they can sign up on this webpage here.
If you have any questions, comments or feedback you can get in touch by phone on 0800 353 824 or email us at SH2Wairarapa@nzta.govt.nz.
|
||
|
|