View online |
O Mahurangi - Penlink |
30 August 2024 |
Wēiti River Bridge updateAs you may know, we are forecasting a delay to the Wēiti River Bridge component of the project of at least 12 months. The rest of the project is still on track for completion by late 2026, and will provide improved access to residents of Stillwater and others along the corridor. We have already undertaken several initiatives to mitigate the programme delay, including design optimisation, construction methodology improvements, and forward resource planning. We acknowledge this is a significant delay and will be disappointing to the Whangaparāoa Peninsula community. However, we can assure you that the team is working efficiently and is continuing to explore initiatives to improve the programme. We expect to have more certainty on the implications of this delay in the coming months and will update you when we have more information. Thank you for your understanding as we work to establish an updated project programme. Please reach out to us with any questions or comments by emailing us at omahurangi@nzta.govt.nz. |
||
7 months of progress in 5 minutesThe team have made big progress over the last 7 months. Check out the video above to see the changes taking place across site by comparing drone footage from November 2023 and June 2024. |
||
(Left) Duck Creek Road bridge team pouring deck concrete with boom pump, (top right) team carrying out final reinforcing inspection, (bottom right) broom finish applied to bridge deck. Duck Creek Road bridge taking shapeWork at the Duck Creek Road bridge is progressing well, with the structures team recently carrying out a successful concrete pour. Once complete, the Duck Creek Road bridge will be one of New Zealand's longest single span concrete bridges at 49 metres long and 12 metres wide, with two traffic lanes and a shared path. This concrete deck pour is the first of five local bridges within the project. A local bridge is one that connects to local roads across the project versus the Wēiti River bridge, which has a large span across the river. The Duck Creek Road bridge is being built using a top down construction method, meaning the piles and bridge deck are constructed first, then the earth is excavated from beneath it. The construction of the bridge deck started by placing 32 precast deck panels onto the bridge girders. Then 40 tonnes of deck reinforcing steel was placed on top of the panels by a team of 16 steel fixers, tying the girders and deck panels together. On pour day, 27 concrete trucks delivered 125 cubic metres of concrete to the Duck Creek Road bridge site. A team of 8 concrete placers and a 49 metre concrete boom pump placed the deck concrete which was up to 250mm thick. The placing team completed the pour with a broom finish to the 600 square metres of bridge deck. All in all, the concrete pour took 10 hours to complete. |
||
Wēiti River channel re-openingWork to establish the temporary staging platform on the eastern side of Wēiti River has progressed well and the channel is now open. While the channel is open, vessels travelling upstream of the worksite will pass through a restricted navigable gap between the eastern and western sections of the temporary platform – see map above. During our working day as construction continues, loads will regularly be lifted over the navigable gap requiring the channel to be intermittently closed for short durations at these times. This is to keep all river users safe and ensure no vessel passes beneath a suspended load. Our working hours are Monday to Friday, 7am to 6pm, and Saturday 8am to 4pm. Passage via the navigable gap within the construction zone Key details for all private vessels including kayaks, stand-up paddle boards and dinghies are:
Future temporary closures Later this year, (November/December) a second temporary closure will be required. This will be for a shorter duration, 4 weeks of work, and will not affect the Christmas and New Year period. |
||
This visualisation of the new O Mahurangi / Whangaparāoa Road intersection is an artist’s impression for illustrative purposes only. It may not be complete or fully accurate and should not be used for technical purposes. Upgrading the Whangaparāoa intersectionWhangaparāoa is undergoing crucial improvements to create the future intersection of O Mahurangi at Whangaparāoa Road. The Whangaparāoa intersection is designed to enhance safety, traffic flow and stormwater management. Key improvements include:
Stormwater wetlands will capture and treat stormwater run-off from road surfaces, reducing the risk of flooding in this low-lying area. Currently, flood waters go over the top of Whangaparāoa Road in a 1 in 10-year storm event. The new design will keep the intersection operating during a 1 in 100-year event, and the wetland areas will also feature ponds, landscaping and pathways. Construction of the new intersection is underway and taking place next to the existing road, to allow traffic to continue to use Whangaparāoa Road. Temporary traffic management will be in place and we expect there to be some impacts when transporting goods to site and later when connecting the new road to existing infrastructure. However, our work has been carefully planned to keep disruption to Whangaparāoa Road to a minimum. We thank you for your patience during this time and apologise for any inconvenience caused. At this stage, the new road alignment at Whangaparāoa Road will be complete by late 2026, however the traffic signals will not be operational and a barrier will be put in place to avoid access onto the completed section of road until the bridge portion of O Mahurangi Penlink is complete. |
||
Various Girls with High Vis site visit activities and group photo next to the Duck Creek Road Bridge. Girls with High Vis visitWe recently hosted 13 secondary school students from Girls with High Vis for an informative and engaging site visit. The Girls with High Vis initiative gives female students around the country the opportunity to gain hands-on experience, hear from inspirational women in the industry and learn what a career in the infrastructure industries, as well as other important trade sectors, can offer. The visit saw the students get construction-site ready with boots, hard hats, safety glasses and safety vests. After a site induction, they split into groups to rotate through four stations. The activities at the stations were planned to showcase different parts of the project:
Auckland Councillor Angela Dalton provided a talk and encouraged them to consider a career in a traditionally male-dominated field. The group then participated in a question and answer session with some of our female project engineers. At the end of the visit, the students said they had a better understanding of infrastructure and what future possibilities the industry offered. Survey results revealed that before the event most students only knew ‘a little’ about infrastructure. After the event, almost all said ‘yes, I better understand what infrastructure is.’ |
||
More information |
||
For more information on the O Mahurangi project, contact us at omahurangi@nzta.govt.nz or call us on 0800 7365 465. Visit our website www.nzta.govt.nz/penlink |
||
|
|