Crews have been drilling and installing steel spiral and concrete piles as works continue on the construction of a MSE (Mechanically Stabilised Earth) wall, along with associated drainage upgrades on Queen Charlotte Drive near Cullen Point, Mahakipawa Hill.
Please note this closure has been extended by one week due to delays caused by the ground conditions when boring the 8 metre deep holes for this site.
The closures will remain in place until Wednesday 6 March, excluding Sunday 3 March, from 9.00am to 3.00pm. Openings will be on the hour, every hour to clear waiting traffic.
The crew are working to complete the works requirng the closure, as quickly as possible. An update will be sent on Friday afternooon via Antenno.
Outside of these times, works will continue under stop/go traffic management, please expect delays.
In addition to the above closures, there will be increased works along the length of Queen Charlotte Drive during March with multiple recovery sites under construction.
Works to install a new culvert and repair the road are continuing, just prior to Moenui Road (when travelling from Havelock). Last week preparation works continued downstream for the culvert installation and two segments of the box culvert were installed. This week culvert outlet work has been carried out, along with installing wing walls and rock protection. The third section of the box culvert is scheduled to be installed next week. These works are under stop/go traffic management.
Works to realign the road and repair a slip have begun 70m past Governors Bay when travelling towards Picton. Over the past three weeks crews have been drilling and installing anchors at this location. These works are scheduled to continue next week.
Works continue at a new retaining wall site, 450m past Aussie Bay. This week backfilling and drainage works have been carried out. Next week backfilling and road preparation works are scheduled at this location.
Works are scheduled to begin next week 750m past The Grove Jetty, when travelling towards Picton to complete drainage upgrades and repair a dropout.
The construction of two railway iron walls is being carried out approximately 1.9 km and 2.1km past Tepuia Heights, on Queen Charlotte Drive when travelling towards Picton. Users of the Link Pathway will be guided through the above sites by traffic management.
A third railway iron site is also scheduled to start in the coming weeks, 450m before Moenui Road, when travelling towards Picton.
Please note there will be increased truck movements while these works are being carried out. Please plan ahead for delays.
Please ensure you keep within the posted traffic speed limits through our worksites to ensure the safety of crews and road users. We thank you for your patience.
|