As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street.

St Aubins Square 

  • Construction of kerb and gutter including new driveway accesses
  • Earthworks to underside of concrete paving
  • Construction of footings for Trellis structure

Kelly St Block 2 West (Liverpool to St Aubins)

  • Continuation of stormwater drainage upgrade
  • Commencement of water main upgrade works
  • Commencement of concrete pavement reinstatement and construction of kerb and gutter

Kelly St Block 1 West (Kingdon to Liverpool) 

  • Submission of traffic guidance scheme to TfNSW for approval
  • Implementation of detour upon approval
  • Commencement of saw cutting and concrete pavement removal.

We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.

Thank you for your ongoing support.

 
Find out more
 
 

Stay tuned for more information on this transformative project. 

 
 
 
Ozone
 

Upper Hunter Shire Council

135 Liverpool Street

Scone  NSW  2337

Media Contact:
Luke Tuxford

ltuxford@upperhunter.nsw.gov.au

 

Other enquiries

council@upperhunter.nsw.gov.au

(02) 6540 1100

You are receiving this email as you are subscribed to Scone CBD Project Updates.  If you know longer wish to receive this update please select unsubscribe.

Preferences  |  Unsubscribe