As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street.
May Progress Summary
St Aubins Town Square
Block 1 (Kingdon to Liverpool Streets) – West & Medians
- Street furniture installation (containment fence)
Block 1 (Kingdon to Liverpool Streets) – East
- Commencement of PVC stormwater lines
- Installation and commissioning of Ausgrid upgrade works
- Installation of private electrical works
Adjustment of Telstra assets
Base course infill
Stormwater pit construction
Commencement of landscape wall
Block 2 (Liverpool to St Aubins Streets) – West & Medians
- Street furniture installation (containment fence)
Block 2 (Liverpool to St Aubins Streets) – East
- Construction of kerb and gutter 95%
- Continuation of footpath works (approx. 60% complete)
- Installation of kerb side lighting adjacent to Liverpool St Intersection
- Landscaping preparation
- Installation of water meters and boxes
- Installation of paver banding and Equine Walk of Fame plaques
- Storm water pit construction
Liverpool St Drainage
Implementation of Liverpool St closure
Installation of box culvert bases and crown units
Commencement of storm
water drainage pits
Works Planned for June
St Aubins Town Square
- Completion of remaining concrete panels
Block 1 (Kingdon to Liverpool Streets) – West & Medians
- Street furniture installation (bubblers and containment fence)
- Finishing and defect works
Block 1 (Kingdon to Liverpool Streets) – East
Completion of kerb and gutter
Completion of PVC storm water connections
Installation of kerb side street lighting adjacent to Liverpool St intersection
Commencement of footpath
construction
Traffic control signal posts upgrade
Block 2 (Liverpool to St Aubins Streets) – West & Medians
Block 2 (Liverpool to St Aubins Streets) – East
Continuation of footpath
TfNSW pavement rectification works
Continued installation of paver banding and Equine Walk of Fame plaques
Landscaping
Traffic control signal posts upgrade
Commence demo and landscape wall outside Royal Hotel
Liverpool St Drainage
We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.
Thank you for your ongoing support.