Scone CBD Revitalisation
 
 

Project Update
June 2024

As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street. 

May Progress Summary

St Aubins Town Square

  • Footpath construction (ongoing)
  • Preparation for final concrete bays

  • Installation of Scone Horse of the Year plaques

Block 1 (Kingdon to Liverpool Streets) – West & Medians

  • Street furniture installation (containment fence)

Block 1 (Kingdon to Liverpool Streets) – East

  • Commencement of PVC stormwater lines
  • Installation and commissioning of Ausgrid upgrade works
  • Installation of private electrical works
  • Adjustment of Telstra assets

  • Base course infill

  • Stormwater pit construction

  • Commencement of landscape wall

Block 2 (Liverpool to St Aubins Streets) – West & Medians

  • Street furniture installation (containment fence)

Block 2 (Liverpool to St Aubins Streets) – East

  • Construction of kerb and gutter 95%
  • Continuation of footpath works (approx. 60% complete)
  •  Installation of kerb side lighting adjacent to Liverpool St Intersection
  • Landscaping preparation
  • Installation of water meters and boxes
  • Installation of paver banding and Equine Walk of Fame plaques
  •  Storm water pit construction

Liverpool St Drainage

  • Implementation of Liverpool St closure

  • Installation of box culvert bases and crown units

  • Commencement of storm water drainage pits

Works Planned for June

St Aubins Town Square

  • Completion of remaining concrete panels

Block 1 (Kingdon to Liverpool Streets) – West & Medians

  • Street furniture installation (bubblers and containment fence)
  • Finishing and defect works

Block 1 (Kingdon to Liverpool Streets) – East

  • Completion of kerb and gutter

  • Completion of PVC storm water connections

  • Installation of kerb side street lighting adjacent to Liverpool St intersection

  • Commencement of footpath construction

  • Traffic control signal posts upgrade

Block 2 (Liverpool to St Aubins Streets) – West & Medians

  • Street furniture installation (bubblers and containment fence) Finishing and defect works

Block 2 (Liverpool to St Aubins Streets) – East

  • Continuation of footpath

  • TfNSW pavement rectification works

  • Continued installation of paver banding and Equine Walk of Fame plaques 

  • Landscaping

  • Traffic control signal posts upgrade

  • Commence demo and landscape wall outside Royal Hotel

Liverpool St Drainage

  • Backfill of culverts

  • Construction of storm water pits

  • Base course replacement

  • Reopen Liverpool St to traffic

We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.

Thank you for your ongoing support.

Scone CBD Revitalisation
 
Find out more
 
 

Stay tuned for more information on this transformative project. 

 
 
 
Ozone
 

Upper Hunter Shire Council

135 Liverpool Street

Scone  NSW  2337

Media Contact:
Luke Tuxford

ltuxford@upperhunter.nsw.gov.au

 

Other enquiries

council@upperhunter.nsw.gov.au

(02) 6540 1100

You are receiving this email as you are subscribed to Scone CBD Project Updates.  If you know longer wish to receive this update please select unsubscribe.

Preferences  |  Unsubscribe