This newsletter is to help inform our Marin Community College District community of the District’s progress on the implementation of the voter‐approved Measure B bond. The improvements made possible by this bond allow us to continue our commitment to educational excellence in providing equitable opportunities and fostering success for all members of our diverse community.

 

Bolinas Marine Laboratory

Visual Renderings

Status Update:

  • Submitted project for County of Marin Planning Review on December 13, 2019
  • Received initial Planning Department review comments on January 10, 2020
  • Community EIR and Project follow up meeting held on March 2, 2020
  • Geotechnical preliminary report in process to meet Planning request
  • Architectural Historian report in process to meet Planning request
  • Resubmission to County of Marin Planning Department estimated to be by May 25, 2020 
 

Projects in Design:

 

New Learning Resources Center Building | Kentfield Campus

Project Summary: Demolition of existing and construction of new Learning Resource Center building

Status:

  • Board of Trustees approve architecture firm contract on December 17, 2019
     
  • Communication Plan pending approval
     
  • Targeting completion of Environmental Impact Report by June 2020
     
  • Abatement & Demolition expected Summer 2020
     
  • Anticipated DSA submittal for new building by March 2021

Environmental Impact Report (EIR) Meetings:

At this time the College has held all 6 of their EIR meetings. You can watch a video of the information presented at both the March 18, 2020 and the March 25, 2020 meetings. Thank you to those who participated.

Townhall Meetings:

  • Integrated Learning Resources Center + Student Services:


    March 24, 2020 Meeting Presentation (PDF, 359MB)

    March 24, 2020 Handout form with 2 slides per page (PDF, 97MB)
     

  • Community Input Survey:
    Share your input through the community survey
     
  • Community Video Presentation:
    https://vimeo.com/400695782

 

 

Admin Cluster - Building 12 Renovation | Indian Valley Campus

Project Summary: Renovation to create café and student spaces

Status:

  • Occupants have vacated
  • Abatement work complete
  • Interior demolition complete
  • Interior design in review
 

Projects currently under construction:

 

Jonas Center and Building 18 | Indian Valley Campus

Project Summary: Event facility to seat 300 people, includes a catering kitchen, a prep kitchen, stage and meeting rooms

Status:

  • Interior finishes and exterior stucco ongoing through April and May
  • Hardscape and paving will be completed in June 2020
 

New Miwok Center - Aquatic & Fitness Center | Indian Valley Campus

Project Summary: Construction of a multi-purpose aquatic fitness facility, with flexible work-out spaces, dance studio, classroom, locker rooms, and offices

Status:

  • Drill and place dive tower piers in April 2020
  • Structural steel for roof arrives in June 2020
  • DSA design review of the dive center complete
 

Maintenance & Operations Building and District Warehouse | Kentfield Campus

Project Summary: District Warehouse and Facilities Administration Building

Status:

  • Storage building and interior finishes in administration building completed in April 2020
  • Landscaping and paving scheduled for May 2020
  • Adjacent site work and fire lane in June 2020
 

Fusselman Hall: Structural and Waterproofing Improvements  | Kentfield Campus

Project Summary: Structural and waterproofing improvements

Status:

  • Exterior excavation and waterproofing through April 2020
  • Landscaping and cleanup in June 2020
 

Learning Resources Center (LRC): Temporary Campus Bookstore  | Kentfield Campus

Project Summary: Renovation of existing Maintenance & Operations building for use as the temporary campus bookstore during demolition of the LRC

Status:

  • Exterior painting and interior finishes in March 2020
  • Store relocates to new space in April 2020
 

Swing Space: Temporary Offices and Classrooms, Increment 2,3  | Kentfield Campus

Project Summary: Relocation of portable classrooms and installation of new 40'x70' temporary classroom

Status:

  • Punchlist ongoing
 

Projects bidding Spring 2020:

 

Learning Resources Center:

  • Stormwater Pollution Prevention Plan (SWPPP) Consultant | Kentfield Campus
  • Lease-Leaseback Request for Proposal Expected to be released in early April 2020
 

For any questions or comments regarding current or future projects, please contact:

Isidro Farias
Director of Capital Projects
(415) 485-9518
ifarias@marin.edu

 
Marin Community College District
1800 Ignacio Blvd., Novato, CA 94949
If you would like to stop receiving Measure B Bond Program updates, please use the "unsubscribe" link at the bottom of this email.
  Share 
  Tweet 
  Share 
  Forward 
Unsubscribe