Measure B Bond Program Newsletter No images? Click here Measure B NewsletterThis newsletter is to help inform our Marin Community College District community of the District’s progress on the implementation of the voter‐approved Measure B bond. The improvements made possible by this bond allow us to continue our commitment to educational excellence in providing equitable opportunities and fostering success for all members of our diverse community. Bolinas Marine Laboratory Visual Renderings Status Update:
Projects in Design: New Learning Resources Center Building | Kentfield Campus Project Summary: Demolition of existing and construction of new Learning Resource Center building Status:
Environmental Impact Report (EIR) Meetings: At this time the College has held all 6 of their EIR meetings. You can watch a video of the information presented at both the March 18, 2020 and the March 25, 2020 meetings. Thank you to those who participated. Townhall Meetings:
Admin Cluster - Building 12 Renovation | Indian Valley Campus Project Summary: Renovation to create café and student spaces Status:
Projects currently under construction: Jonas Center and Building 18 | Indian Valley Campus Project Summary: Event facility to seat 300 people, includes a catering kitchen, a prep kitchen, stage and meeting rooms Status:
New Miwok Center - Aquatic & Fitness Center | Indian Valley Campus Project Summary: Construction of a multi-purpose aquatic fitness facility, with flexible work-out spaces, dance studio, classroom, locker rooms, and offices Status:
Maintenance & Operations Building and District Warehouse | Kentfield Campus Project Summary: District Warehouse and Facilities Administration Building Status:
Fusselman Hall: Structural and Waterproofing Improvements | Kentfield Campus Project Summary: Structural and waterproofing improvements Status:
Learning Resources Center (LRC): Temporary Campus Bookstore | Kentfield Campus Project Summary: Renovation of existing Maintenance & Operations building for use as the temporary campus bookstore during demolition of the LRC Status:
Swing Space: Temporary Offices and Classrooms, Increment 2,3 | Kentfield Campus Project Summary: Relocation of portable classrooms and installation of new 40'x70' temporary classroom Status:
Projects bidding Spring 2020: Learning Resources Center: