Scone CBD Revitalisation
 
 

Project Update
December 2023

As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street. 

The new concrete footpaths are underway and we are progressively working toward completion of the western side of Kelly St between Liverpool and St Aubins.  The paver banding and installation of Equine Walk of Fame plaques will commence in early December.

The second Ausgrid outage was successful and the underground power on the western side of Kelly St between Kingdon and Liverpool St has been upgraded.  Thanks to all the business owners for your cooperation, patience and assistance on the day.  That concludes the services upgrade for this block (electrical, water, communications and street lighting).

Progress Summary

St Aubins Town Square

  • Installation of new streetlights

Block 2 - West

  • Completion of final Telstra pit adjustments
  • Installation of tree pits
  • Installation of trench grates
  • Construction of footpath
  • Construction of pram ramps
  • Continuing construction of median island kerb
  • Construction of median infill
  • Installation of planter boxes (including irrigation and drainage)

Block 1 - West

  • Completion of Ausgrid cable install in preparation for cut over on the 26 November 2023
  • Completion of base course replacement 
  • Installation of tree pits
  • Installation of trench grates
  • Continues construction of landscaping walls
  • Construction of median island kerb
  • Construction of median infill

Next period’s planned activity summary

St Aubins Town Square

  • Commissioning of new streetlights
  • Removal of Ausgrid street light and finishing surrounding concrete

Block 2 – West

  • Completion of footpath construction 
  • Construction of paver banding and horse plaque installation
  • Completion of median islands and planter boxes

Block 1 - West

  • Continuing construction of median islands
  • Continuing construction of landscape walls
  • Construction of pedestrian crossing at Coles
  • Commencement of concrete footpath works

Note the Contractor will be shutting down for Christmas between the 22nd of December to the 2nd of January.

We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.

Thank you for your ongoing support.

Scone CBD Revitalisation
 
Find out more
 
 

Stay tuned for more information on this transformative project. 

 
 
 
Ozone
 

Upper Hunter Shire Council

135 Liverpool Street

Scone  NSW  2337

Media Contact:
Luke Tuxford

ltuxford@upperhunter.nsw.gov.au

 

Other enquiries

council@upperhunter.nsw.gov.au

(02) 6540 1100