Scone CBD Revitalisation
 
 

Project Update
May 2023

As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street.

  • Works in St Aubins square will be continuing with construction of stormwater, kerb and the footings for the new trellis structure.
  • Works on the west side of Kelly St between Liverpool St and St Aubins will continue with construction of stormwater drainage and the installation of the new water main service.
  • The contractor is also preparing its traffic guidance scheme for commencement of the west side of Kelly St  between Kingdon and Liverpool for submission to Transport for NSW.  Depending on the approval timeframe, this next stage will commence by the end of the month.

We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.

Thank you for your ongoing support.

 
Find out more
 
 

Stay tuned for more information on this transformative project. 

 
 
 
Ozone
 

Upper Hunter Shire Council

135 Liverpool Street

Scone  NSW  2337

Media Contact:
Luke Tuxford

ltuxford@upperhunter.nsw.gov.au

 

Other enquiries

council@upperhunter.nsw.gov.au

(02) 6540 1100

You are receiving this email as you are subscribed to Scone CBD Project Updates.  If you know longer wish to receive this update please select unsubscribe.

Preferences  |  Unsubscribe