Measure B Newsletter

This newsletter is to help inform our Marin Community College District community of the District’s progress on the implementation of the voter‐approved Measure B bond. The improvements made possible by this bond allow us to continue our commitment to educational excellence in providing equitable opportunities and fostering success for all members of our diverse community.

 

Resolution No. 2020-17 

A public hearing was held at the June 16, 2020 Board meeting to allow public comments on the Learning Resources Center (LRC) Environmental Impact Report (EIR). The Board of Trustees approved Resolution No. 2020-1, certifying the Facilities Master Plan (FMP) and Learning Resources Center (LRC) Environmental Impact Report (EIR); Adopting the Statement of Facts and Findings, Statement of Overriding Considerations, and Mitigation Monitoring Program; Approving the FMP; and Approving the LRC Project.

More information can be found here

 

Bolinas Marine Laboratory

Visual Renderings

Status Update:

  • Submitted project for County of Marin Planning Review on December 13, 2019
  • Received initial Planning Department review comments on January 10, 2020
  • Community EIR and Project follow up meeting held on March 2, 2020
  • Geotechnical preliminary report in process to meet Planning request
  • Architectural Historian report in process to meet Planning request
  • Resubmission date to the County of Marin was extended until August 24, 2020
 

Projects in Design:

 

New Learning Resources Center Building | Kentfield Campus

Project Summary: Demolition of existing and construction of new Learning Resources Center building

Status:

  • Design contract placed on a temporary hold until August 2020
  • Exterior abatement & building demolition expected to start June 17, 2020 and be completed by mid-September
  • Trees that are diseased and dying will be removed. For every tree removed, two more will be planted on the campuses.
 

Admin Cluster - Building 12 Renovation | Indian Valley Campus

Project Summary: Renovation to create café and student spaces

Status:

  • Occupants have vacated
  • Abatement work complete
  • Interior demolition complete
  • Interior design temporarily on hold
 

Projects currently under construction:

 

Jonas Center and Building 18 | Indian Valley Campus

Project Summary: Event facility to seat 300 people, includes a catering kitchen, a prep kitchen, stage and meeting rooms

Status:

  • Pavers, site benches, and punch list in July
  • Commissioning and final completion in August
 

New Miwok Center - Aquatic & Fitness Center | Indian Valley Campus

Project Summary: Construction of a multi-purpose aquatic fitness facility, with flexible work-out spaces, dance studio, classroom, locker rooms, and offices

Status:

  • Structural steel, columns and beams, main roofing ongoing through August
  • Underground plumbing, concrete footing formwork, concrete surge pits, retaining walls, slab on grade ongoing through August
 

Maintenance & Operations Building and District Warehouse | Kentfield Campus

Project Summary: District Warehouse and Facilities Administration Building

Status:

  • Interior punch list corrective work to be completed by late June
  • Adjacent site work and fire lane to be completed by the end of July
 

Fusselman Hall: Structural and Waterproofing Improvements  | Kentfield Campus

Project Summary: Structural and waterproofing improvements

Status:

  • Interior punch list corrective work to be completed in late June
  • Exterior landscaping and punch list in July
 

Learning Resources Center (LRC): Temporary Campus Bookstore  | Kentfield Campus

Project Summary: Renovation of existing Maintenance & Operations building for use as the temporary campus bookstore during demolition of the LRC

Status:

  • Store has been relocated to new space and minor punch list items have been completed
 

Projects bidding Spring/Summer 2020:

 

Learning Resources Center:

  • Stormwater Pollution Prevention Plan (SWPPP) Consultant | Kentfield Campus
  • Lease-Leaseback Request for Proposal Expected to be released in June 2020
 

For any questions or comments regarding current or future projects, please contact:

Isidro Farias
Director of Capital Projects
(415) 485-9518
ifarias@marin.edu

 
Marin Community College District
1800 Ignacio Blvd., Novato, CA 94949
If you would like to stop receiving Measure B Bond Program updates, please use the "unsubscribe" link at the bottom of this email.
  Share 
  Tweet 
  Share 
  Forward 
Unsubscribe