Scone CBD Revitalisation
 
 

Project Update
September 2023

As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street. 

Pedestrian management will be changing in Block 2 (Liverpool to St Aubins Streets).  The Contractor requires access to the footpath adjacent to the shops for the installation of the upgraded electrical network and modifications to Telecommunications infrastructure.  This will involve varying the route pedestrians take but access to businesses will be maintained throughout.

General Construction Update

Progress Summary

St Aubins Town Square 

  • Commencement of footpath construction

  • Completion of piling and footing construction for trellis structure

  • Installation of streetlight footings and conduits

Block 2 - West (Liverpool Street to St Aubins Street)

  • Reinstatement of base course infill

  • Removal of median islands

  • Construction of landscape walls

Block 1 West – (Kingdon Street to Liverpool Street)

  • Completion of storm water drainage upgrade 

  • Construction of subsoil drainage and sub base pavement replacement 

  • Installation and cutover of new 150mm water main

  • Removal of median islands

  • Installation of temporary roundabout at intersection of Kingdon and Kelly Streets

Next period’s planned activity summary

Completion of works at the park including:

  • Construction of concrete paving

  • Construction of Trellis structure

  • Completion of soft works (turf, plants and trees)

Continuation of works on Block 2 (the west side of Kelly Street between Liverpool and St Aubins Streets) including:

  • Pedestrian management change to access footpath adjacent to the building line.

  • Construction of remaining services (electrical, street lighting, communications)

Continuation of works on Block 1 (west side of Kelly Street between Kingdon and Liverpool Streets) including:

  • Placement of kerb and gutter

  • Reinstatement of base

With the securing of additional funding, the scope is being expanded.  The contract is being altered to include new traffic signals and landscaped median islands.  To manage this additional scope, the delivery dates are changing. Updated project schedule is available on our dedicated project page: upperhunter.nsw.gov.au/sconecbd

We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.

Thank you for your ongoing support.

Scone CBD Revitalisation
 
Find out more
 
 

Stay tuned for more information on this transformative project. 

 
 
 
Ozone
 

Upper Hunter Shire Council

135 Liverpool Street

Scone  NSW  2337

Media Contact:
Luke Tuxford

ltuxford@upperhunter.nsw.gov.au

 

Other enquiries

council@upperhunter.nsw.gov.au

(02) 6540 1100

You are receiving this email as you are subscribed to Scone CBD Project Updates.  If you know longer wish to receive this update please select unsubscribe.

Preferences  |  Unsubscribe