As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street.
Pedestrian management will be changing in Block 2 (Liverpool to St Aubins Streets). The Contractor requires access to the footpath adjacent to the shops for the installation of the upgraded electrical network and modifications to Telecommunications infrastructure. This will involve varying the route pedestrians take but access to businesses will be maintained throughout.
General Construction Update
Progress
Summary
St Aubins Town Square
Commencement of footpath construction
Completion of piling and footing construction for trellis structure
Installation of streetlight footings and conduits
Block 2 - West (Liverpool Street to St Aubins Street)
Reinstatement of base course infill
Removal of median islands
Construction of landscape walls
Block 1 West – (Kingdon Street to Liverpool Street)
Completion of storm water drainage upgrade
Construction of subsoil drainage and sub base pavement replacement
Installation and cutover of new 150mm water main
Removal of median islands
Installation of temporary roundabout at intersection of Kingdon and Kelly Streets
Next period’s planned activity summary
Completion of works at the park including:
Construction of concrete paving
Construction of Trellis structure
Completion of soft works (turf, plants and trees)
Continuation of works on Block 2 (the west side of Kelly Street between Liverpool and St Aubins Streets) including:
Pedestrian management change to access footpath adjacent to the building
line.
Construction of remaining services (electrical, street lighting, communications)
Continuation of works on Block 1 (west side of Kelly Street between Kingdon and Liverpool Streets) including:
With the securing of additional funding, the scope is being expanded. The contract is being
altered to include new traffic signals and landscaped median islands. To manage this additional scope, the delivery dates are changing. Updated project schedule is available on our dedicated project page: upperhunter.nsw.gov.au/sconecbd
We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.
Thank you for your ongoing support.