October Progress Summary
In October, work in Scone’s CBD moved steadily forward, with key upgrades and improvements in Block 3 between St Aubins and Susan Streets. Thank you for your cooperation as we work to make Scone CBD more accessible for all.
Block 1 and 2 (Kingdon to St Aubins Street)
Block 3 Corner (St Aubins to Susan Streets)
- Completion of kerb and median islands
- Completion of Ausgrid conduits
- Completion of Telstra asset adjustments
- Completion of wombat crossing
- Completion of storm water pits
- Water main replacement
Works Planned for
November
Blocks 1 and 2
Block 3 (St Aubins to Susan Streets) - Stage 2 Works
Footpath construction
Milling to suit design parameters
Median island construction
Irrigation works
Private lighting works
Paver banding, Equine Walk of Fame plaques and landscaping
Asphalt works and line marking
We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.
Thank you for your ongoing support.