Scone CBD Revitalisation
 
 

Project Update
November 2023

As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street. 

The Ausgrid outage was successful and the underground power on the western side of Kelly St between Liverpool St and St Aubins has been successfully upgraded.  Thanks to all the business owners for your cooperation, patience and assistance on the day.  That concludes the services upgrade for this block (electrical, water, communications and street lighting) meaning we are able to start delivering the new concrete footpaths.

The next Ausgrid shutdown for the western side of Kelly St between Kingdon and Liverpool St has been scheduled for 26th November, which will conclude the services upgrade and be another important milestone for the project.

Progress Summary

St Aubins Town Square

  • Completion of landscaping, planting and irrigation
  • Practical completion of St Aubins Square with the main area opened to the public

Block 2 - West

  • Completion of communication pit upgrade works
  • Completion of Ausgrid power upgrade works
  • Completion of water meter installation
  • Completion of streetlight conduits and footings
  • Completion of planter drainage in medians
  • Continuing construction of landscape walls
  • Continuing construction of median island kerb
  • Construction of pram ramps
  • Irrigation conduit install
  • Commencement of footpaths on side streets
  • TfNSW pavement slab rectification works

Block 1 - West

  • Completion of Ausgrid conduit install
  • Completion of available Telstra pit adjustments
  • Construction of base course replacement 
  • Water meter installation
  • Construction of planter drainage and electrical in medians 
  • Construction of landscaping walls
  • Irrigation conduit install
  • TfNSW pavement slab rectification works
  • Construction of median island kerb

Next period’s planned activity summary

St Aubins Town Square

  • Installation of street lighting and concrete
  • Removal of Ausgrid street lighting

Block 2 – West

  • Commencement of footpath construction 
  • Construction of median islands
  • TCS works

Block 1 - West

  • Construction of median islands
  • Continuing construction of landscape walls
  • Construction of pram ramps
  • Ausgrid connection works (cut over planned for Sunday, 26 November 2023)

We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.

Thank you for your ongoing support.

Scone CBD Revitalisation
 
Find out more
 
 

Stay tuned for more information on this transformative project. 

 
 
 
Ozone
 

Upper Hunter Shire Council

135 Liverpool Street

Scone  NSW  2337

Media Contact:
Luke Tuxford

ltuxford@upperhunter.nsw.gov.au

 

Other enquiries

council@upperhunter.nsw.gov.au

(02) 6540 1100

You are receiving this email as you are subscribed to Scone CBD Project Updates.  If you know longer wish to receive this update please select unsubscribe.

Preferences  |  Unsubscribe