As part of our ongoing commitment to keeping you informed about the Scone CBD Revitalisation Project, we would like to share an update on the works happening in and around St Aubins Square and Kelly Street.
We were very pleased to open Block 2 West prior to Christmas and restore access to the businesses on that stretch. Thank you to those businesses for your patience and support. After a short Christmas break, Daracon returned to work on the 3rd January and has been busy progressing works in both Block 1 west and Block 2 east. We are working hard to complete the western side of the road by late February.
Progress Summary
Block 2 - West
Block 1 - West
- Completion of median island kerb and raised pedestrian crossing
- Installation of planter boxes in medians
- Completion of trench
drains
- Commencement of footpath construction
Next period’s planned activity summary
Block 2 – West
Block 2 - East
Block 1 - West
We will continue to provide updates on the project's progress. Please don't hesitate to reach out if you have any questions or concerns.
Thank you for your ongoing support.