Measure X Bond Newsletter

San Benito County Campus Update

Over the past year the Measure X bond program team has been working diligently to keep this project moving forward:

  • Felice Consulting Services is working with local agencies for sewer, water, power, gas and data to be delivered to the site.
  • San Benito County Campus stakeholders, trustees, and community members have been involved in the development of the San Benito County Campus facilities, campus aesthetics, and future development of the site.

  • The full project schedule can be found here.

Design and Construction Schedule:

  • January 2021: Design-Build Contract Approval
  • January - April 2021: Project Steering Meetings
  • April 20, 2021: Planning Taskforce Meeting
  • April 29, 2021: Ad-hoc Meeting
  • May 3, 2021: Community Meeting
  • May 11, 2021: Board of Trustees approval of schematic design documents
  • July 14, 2021: Planning Taskforce Meeting
  • August 10, 2021: Board of Trustees approval of design development documents
  • December 14, 2021: Board of Trustees approval of construction documents
  • January 2022: Submission to Division of State Architect (DSA)
  • November 2022: Start of Construction
  • March 2024: Building Occupancy

Campus Renderings (subject to change):

Entry View

Central Hub: East

South Terrace

Central Hub: Entrance

Community Room

View from South

 

Gavilan College Gilroy Campus Update

Completed Projects

The Fire Alarm Upgrade was completed in November 2021, as part of the Site Improvements, Security and Infrastructure project.

The Pool ADA Upgrades were completed in June 2021 as part of the Site Improvements, Security and Infrastructure project.

Projects in Construction

The Pedestrian Bridge project is underway, also as part of the Site Improvements, Security and Infrastructure main project. The existing bridge is a wood structure and has become structurally unstable due to dry rot. The new bridge will be constructed of steel and concrete, have a longer life span, and will meet current ADA regulations.

  • December 2021: Shop drawings and Steel Mill order
  • January 2022: Offsite fabrication of new bridge
  • February 2022: Demolition of existing bridge
  • March 2022: Construction of new bridge
  • June 2022: Anticipated project completion

The Boiler and Hot Water Piping Replacement project is currently in progress and replaces the failing infrastructure on the Gavilan Gilroy Campus. The newly installed boilers will also reduce emissions and improve air quality.

  • September 2021: Board of Trustees approval of contract
  • November 2021: Temporary boilers installed
  • December 2021: Underground piping installed
  • January 2022: New boilers installed
  • February 2022: Project completion

Upcoming Projects in Design

STEM Center

Modernization of existing facilities and new construction of a Science, Technology, Engineering, and Math (STEM) Center. This project will include general lecture classrooms, science and computer labs, study areas, and faculty and support staff offices.

Schedule:

  • March 2021: Programming started
  • January 2022: Criteria documents to be completed
  • May 2022: Selection of the Design-Build-Entity (DBE) begins
  • January 2023: Design and construction documents to be completed
  • January 2024: Division of State Architect (DSA) review begins
  • November 2024: Start of construction
  • January 2028: Building occupancy

Library and Student Resource Center (LSRC)

Construction of a new, state of the art Library and Student Resource Center. The new Library will replace the aging Library and incorporate Student Services functions into one location.

Schedule:

  • August 2021: Started revised programming
  • January 2022: Criteria documents to be completed
  • April 2022: Selection of the Design-Build-Entity (DBE) begins
  • November 2022: Design and construction documents to be completed
  • November 2023: Division of State Architect (DSA) review begins
  • October 2024: Start of construction
  • November 2026: Building occupancy

Theater Modernization

The Theater Modernization project is home to the theater program, and will include upgrades to the theater, classrooms, scene shop, rehearsal rooms, offices and storage for props and equipment.

Schedule:

  • August 2021: Started programming
  • January 2022: Building assessments begin
  • May 2022: Hazmat investigation begins
  • September 2022: Design and construction documents complete
  • March 2024: Division of State Architect (DSA) review starts
  • March 2025: Construction begins
  • November 2026: Building occupancy

Wayfinding and Signage

This project involves creating bilingual signage throughout the campus, to help improve wayfinding for students, faculty, and campus visitors. This project also includes the construction of a monument sign at the entrance to the campus.
Expected completion: November 2022

Covered Walkways Replacement Project

This project involves the replacement of existing walkway canopies/covers that are structurally failing due to age and dry rot.
Expected completion: September 2023

Measure X Year In Review Video

Thank you!

Gavilan College would like to thank the community for their support in passing Measure X. Along with this opportunity, comes responsibility. The District is committed to the responsible stewardship of all bond funds. Measure X will fund capital improvements that will preserve quality education for years to come. The improvements made possible by this voter-supported bond measure will allow us to continue our mission to assist students in achieving their educational and employment goals.

 