Measure B Bond Program Newsletter

No Images? Click here

 

Measure B Newsletter

This newsletter is to help inform our Marin Community College District community of the District’s progress on the implementation of the voter‐approved Measure B bond. The improvements made possible by this bond allow us to continue our commitment to educational excellence in providing equitable opportunities and fostering success for all members of our diverse community.

 

Projects recently completed or in closeout:

 

Performing Arts: Stage Floor Replacement | Kentfield Campus

This project provided several small capital repairs to the Performing Arts building, including a stage floor replacement.

Status:

  • Punch list complete
  • Cleaning of auditorium seats complete
  • Project completed early and under budget
 

Athletic Synthetic Turf Fields and Restroom/Storage Facilities - Soccer, Volleyball, Futsal | Kentfield Campus

This project involved replacing the existing natural grass field with synthetic turf fields with associated markings for various sports. It also includes a restroom facility, an addition to the gym complex for storage of equipment, score boards, tennis courts, and multi-purpose turf in the PE complex.

Status:

  

  • Maintenance period completed August 3, 2018
  • Closeout documents under review
  • Notice of completion scheduled for August 15, 2018
 

Projects currently under construction:

 

Athletic Synthetic Turf Fields and Restroom/Storage Facilities - Phase 2 Baseball Field | Kentfield Campus

This project replaces the existing natural grass baseball field with a synthetic turf baseball field, as well as construction of a restroom facility, score board and perimeter fencing.

Status:

  • Cutting and grading of field subgrade
  • Soil off-haul
  • Review of electrical and fire alarm scope of work, layout for trenching

Organic Farm/Garden Enhancements | Indian Valley Campus

This project includes the construction of a new prefabricated, pre-DSA (Division of State Architect) approved classroom building for the Organic Farm & Garden's associated programs and demonstrations.

Status:

 

  • Concrete paths and drives complete
  • Classroom electrical complete
  • Relocation of greenhouse and shade structure in progress
  • New farm fence installation in progress
  • Kitchen appliance installation ongoing
  • Furniture delivery in August
  • Demonstration kitchen complete in September
 

Pomo Cluster | Indian Valley Campus

This project involves Buildings 1-7, and includes building envelope improvements, window replacements, mechanical repairs, flooring, painting, and other small capital repairs.

Status:

  • Phase 1: Window painting and punch list complete
  • Phase 2: Buildings 3, 4, 5 and 7 interior renovations. Construction started August 13, 2018.

 

 

Projects currently in design:

 
  • Maintenance & Operations Building and District Warehouse | Kentfield Campus

  • Jonas Center and Building 18 | Indian Valley Campus
  • Fine Arts - Small Capital Repairs | Kentfield Campus
  • New Miwok Center - Aquatic & Wellness Center | Indian Valley Campus
  • Site Improvements and Utilities - PE Fire Lane and Accessible Stalls | Kentfield Campus
  • Student Services / Learning Resources Center | Kentfield Campus
  • Fusselman Hall | Kentfield Campus

For any questions or comments regarding current or future projects, please contact:

Isidro Farias
Director of Capital Projects
(415) 457-8811 Ext. 7518
ifarias@marin.edu

 
Marin Community College District
1800 Ignacio Blvd., Novato, CA 94949
If you would like to stop receiving Measure B Bond Program updates, please use the "unsubscribe" link at the bottom of this email.
  Like 
  Tweet 
  Share 
  Forward 
Unsubscribe